Showing posts with label great barrier reef. Show all posts
Showing posts with label great barrier reef. Show all posts

18 October, 2013

Great Barrier Reef & the Ports Plan

Draft Ports Plan

Many of Qld’s major trading ports are near or adjacent to important environmental values including the Great Barrier Reef.

The Qld Government is attempting to address the United Nations’ Educational, Scientific and Cultural Organisation’s (UNESCO) concerns.

UNESCO raised concerns about the level of development along the Qld coast and its impact on the World Heritage site, including water quality and the loss of coral.

UNESCO recommends that the Australian and Qld Governments restrict port development outside the long-established major port areas within or adjoining the Great Barrier Reef World Heritage Area.

Qld Government’s response includes:


The aim of the draft Qld Ports Strategy is managing and improving the efficiency and environmental management of the state’s port network over the next decade.

The strategic objectives of the draft Qld Ports Strategy include:
  •     providing certainty and direction for future port planning,
  •     supporting environmental protection, in particular for the Great Barrier Reef,
  •     supporting improvements in the management and productivity of ports and the ports network,
  •     enhancing supply chain connections,
facilitating the strategic use of ports.

The key actions are:
  • ·     establishment of Priority Port Development Areas (PPDAs),
  • ·     prohibition of capital dredging for the development of deep water port facilities outside of PPDAs (for ten years),
  • ·     guidance for leading practice master planning for Qld ports.


Along Qld’s 6,973 km coastline, there are 20 ports including 15 trading ports, two community ports, and three gazetted non-trading ports. The PPDAs are proposed for the ports of Brisbane, Mackay/Hay Point (two separate zones), Gladstone, Townsville and Abbot Point.

The Qld Government proposes legislation to be in place by next year to deliver on these commitments. Ports would have to prepare master plans and outline how they will meet Qld and federal environment assessment standards.
The Qld Ports Strategy attempts to align with the National Ports Strategy and relevant international, national, state and local legislation and policy for the responsible and efficient operation of ports. Alignment with the National Ports Strategy is of particular importance as it is designed to improve port and freight infrastructure productivity and attract greater private sector investment. The National Ports Strategy calls for integrated plans across ports.

The Federal Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) used to provide an overarching mechanism for protecting the World Heritage values from inappropriate development, including actions taken inside or outside which could impact on its heritage values.  The Federal Government is in the process of handing over these responsibilities to the State Governments.

Development proposals were required to undergo rigorous environmental impact assessment processes, often including public consultation, after which the Federal Minister may decide, to approve, reject or approve under conditions designed to mitigate any significant impacts.  This may be replaced by a one-stop-shop for Environmental approvals at State level.

A recent amendment to the EPBC Act did make the GBR Marine Park an additional 'trigger' for a matter of National Environmental Significance which provided additional protection for the values within the GBR.

Coal is still the predominant commodity export representing 63 per cent of volumes followed by bauxite at 15 per cent and petroleum products 6 per cent.
The remaining 16 per cent is shared by metals and minerals, general cargo, agriculture and other products.

The draft Qld Ports Strategy has been informed by the results of consultation on the draft Great Barrier Reef Ports Strategy

The main themes of public consultation on the Great Barrier Reef Ports Strategy included:
  • ·       support for the concentration of development to within existing port limits
  • ·       recognition of the important role of ports in facilitating the growth of economies
  • ·       concern for the Great Barrier Reef and threatened species
  • ·       support for improving port planning and master planning
  • ·       support for strengthening protection of land and corridors near ports
  • ·       support for improving environmental management consistently across ports
  • ·       support for strategic alignment in planning activities across jurisdictions, particularly with the National    Ports Strategy.

These key themes and issues raised during the consultation process on the draft Great Barrier Reef Ports Strategy are outlined in the Great Barrier Reef Ports Strategy - Summary of Consultation Responses Report.


The draft Qld Ports Strategy will be open for public comment until 13 December 2013. For more information and to complete an online survey to have your say visit: www.dsdip.qld.gov.au/qps



23 June, 2013

Great Barrier Reef

The 37th session of the World Heritage Committee is sitting in the Kingdom of Cambodia, in Phnom Penh and Siem Reap-Angkor, from 16th to 27th June 2013.

 

The 37th session is organized by UNESCO and the National Commission of Cambodia with the support of the Presidency of the Council of Ministers.


Last week the World Heritage Committee has delayed its decision on whether to list the Great Barrier Reef as ‘in danger’.

The Federal Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) provides an overarching mechanism for protecting the World Heritage values from inappropriate development, including actions taken inside or outside which could impact on its heritage values. This requires any development proposals to undergo rigorous environmental impact assessment processes, often including public consultation, after which the Federal Minister may decide, to approve, reject or approve under conditions designed to mitigate any significant impacts.

A recent amendment to the EPBC Act makes the GBR Marine Park an additional 'trigger' for a matter of National Environmental Significance which provides additional protection for the values within the GBR.

The Qld Government has welcomed the opportunity to continue our initiatives while further considerations are made over the next year.

The 2009 Outlook Report identified the long-term challenges facing the GBR; these are dominated by climate change over the next few decades.
The extent and persistence of damage to the GBR ecosystem will depend to a large degree on the amount of change in the world’s climate and on the resilience of the GBR ecosystem to such change. This report also identified continued declining water quality from land-based sources, loss of coastal habitats from coastal development, and some impacts from fishing, illegal fishing and poaching as the other priority issues requiring management attention for the long-term protection of the GBR.

Emerging issues since the 2009 Outlook Report include proposed port expansions, increases in shipping activity, coastal development and intensification and changes in land use within the GBR catchment; population growth; the impacts from marine debris; illegal activities; and extreme weather events including floods and cyclones.

Further building the resilience of the GBR by improving water quality, reducing the loss of coastal habitats and increasing knowledge about fishing and its effects and encouraging modified practices, will give the GBR its best chance of adapting to and recovering from the threats ahead, including the impacts of a changing climate.

The Qld Government is attempting to address UNESCO’s concerns and deliver on their recommendations.

They include:
·       Establishing a scientific panel to monitor Gladstone Harbour as part of a $4 million Gladstone Healthy Harbour Partnership,
·       Committing $35 million each year for reef protection and improved water quality,
·       Releasing a draft Ports Strategy that clearly states our intention to limit port development to existing areas.

The Qld Government has implemented a best management practice programs with the agricultural industry to reduce nutrient run off and improve water quality.




06 June, 2013

Qld Budget



Qld Budget

The Qld Government Budget paper No.4 provides a consolidation of expense, capital and revenue measures reflecting decisions by the Qld Government since the 2012-13 austerity Budget.

The following is summary of some of the highlights of measures of the Qld Government concerning the Environment.

The Qld Government will provide additional net funding of $1.7m over four years, which together with existing funding will provide a total of $4.6m over four years to coordinate, develop and implement The Queensland Plan: a 30 year vision for Queensland which will inform the Government's response and future policy program.

CSG

The Office of Best Practice Regulation (OBPR) will undertake a comprehensive review of the State's approach to Coal Seam Gas industry regulation.  The OBPR will develop options for cost recovery.

The Department of Environment and Heritage Protection will receive $3.7m for the regulation and administration of the Coal Seam Gas industry.  A total of $11m for CSG regulation is spread across the following departments:
·  Environment and Heritage Protection
·  Energy and Water Supply,
·  Natural Resources and Mines and
·  State Development, Infrastructure and Planning.

Gladstone Harbour and the Reef

The Qld Government will provide an additional $4m over two years towards the Gladstone Healthy Harbour Partnership, investigating the hydrodynamic, biogeochemistry, marine biodiversity, water quality, marine toxicology, ecosystem health and decision support and modelling.

The funds are subject to an industry contribution of $1.5m per year (total of $3m) in funding for collaborative action between Government, the community and industry to maintain and continuously improve harbour health.

The Qld budget has increased funding of $2.8m over three years from 2014-15 for the coordination of the Reef Water Quality Protection Plan. The Plan aims to conserve this internationally recognised world heritage site from the impact of poor water quality by promoting land management improvements including the reduction of wasteful run-off of fertilizers, pesticides and soil.

The Federal Government has also progressed an independent and public review of environmental management arrangements and governance of Qld's Port of Gladstone.

The Qld Government will provide funding of $80m over five years from 2013-14 towards natural resource management investment in Qld including initiatives to protect the Great Barrier Reef. 

Incidentally, the Federal Government renewed its commitment to protecting the Great Barrier Reef with the State Party Report on the Great Barrier Reef World Heritage Area.

The Federal and Qld Governments are currently progressing draft strategic assessment and program reports and these will be released for public comment in the first half of the year.


Waterways, Resilience and other Measures

There is increased funding of $8m over four years commencing in 2013-14 towards the South East Queensland (SEQ) Healthy Waterways Partnership. This program will provide project funding for water quality improvement and waterway resilience across SEQ including Moreton Bay. Projects will run in partnership with local governments, Healthy Waterways Ltd and SEQ Catchments.
Following on from floods and cyclones, the Qld Government is providing additional funding of $40m towards the Betterment Fund which will support the building of stronger, more resilient infrastructure. The Federal Government is matching the funding provided by the Government so that the total value of the program is $80m.

The Government is providing increased funding of $41.7m over two years for the continuation of the Qld Reconstruction Authority through to 30 June 2014.

The Qld Government is providing additional funding of $3.9m over three years and has approved the reallocation of $0.55m for the establishment of the Community Resilience Team. The team will provide effective coordination, governance and reporting of the whole-of-Government response to the 2012-13 natural disasters and to oversee community resilience activities across Qld.

The Qld Government is providing additional funding of $1m over three years and has approved the reallocation of $0.32m for the appointment of three Disaster Recovery Coordinators. These officers will provide a coordinated approach to the recovery and rebuilding of Qld following the 2012-13 natural disasters.

The Qld Government will provide increased funding of $15.9m over four years from 2013-14 for the implementation of joint park management and maintenance for lands to be declared protected areas under the Cape York Peninsula Tenure Resolution Program. Further funding for this measure was allocated to the Department of Aboriginal and Torres Strait Islander and Multicultural Affairs.


The Qld Government has approved the reallocation of $1.4m in 2013-14 to establish the Building and Construction Compliance Branch with responsibility for monitoring, educating, reporting and ensuring compliance with the Qld Code of Practice for the Building and Construction Industry.



01 December, 2012

My letter from the Office of the Hon Jeff Seeney MP

on the 26 October 2012, I wrote to the Deputy Premier, in response to his media release which stated:


Mr Seeney said the assessment showed that well-managed development could co-exist with a healthy environment. “It illustrates that we can have bulk export ports and they can operate with no threat to the Great Barrier Reef,” Mr Seeney said. 
Mr Seeney seems to have completely missed the point.  The greatest threat to the Great Barrier Reef are not from the port operations but from accumulative impacts of the continued combustion of fossil fuels.





On  26 November 2012, I received the following response from:

Office of the Hon Jeff Seeney MP
Deputy Premier
Minister for State Development, Infrastructure and Planning


Our ref: MC12/399

23 NOV 2012

Mr Rowan Barber
Street Address
Address QLD XXXX


Dear Mr Barber

Thank you for your email of 26 October 2012 to the Honourable Jeff Seeney MP, Deputy Premier, Minister for State Development, Infrastructure and Planning, about the voluntary Abbot Point Cumulative Impact Assessment (CIA).  The Deputy Premier has asked that I respond on his behalf.

As you are aware, the voluntary Abbot Point CIA has focus on 16 study areas, and is taking a holistic look at the cumulative effects of the future port related expansion proposals at the Port of Abbot Point.

The CIA scope is about port expansion itself.  Emissions associated with the transport of coal to the port are not within the scope of the CIA.  It was a voluntary cooperative exercise between the three proponents of the existing or proposed facilities at Abbot Point.  It was coordinated by the North Queensland Bulk Ports Corporation.

I suggest you provide comments to the Abbot Point Working Group through the formal consultation process on this matter.  The following link provides information on making a submission  http://www.abbotpointworkinggroup.com.au/comment.html.

Please ensure your comments are submitted prior to 5pm, Tuesday, 4 December 2012.

If you require any further information, please contact Mr Phillip Kohn, A/Director, State Development Areas, Office of the Coordinator General, Department of State Development, Infrastructure and Planning, on 3405 6674, who will be pleased to assist.

Yours sincerely


Dimity Elson
Acting Senior Policy Advisor

Office of the Hon Jeff Seeney MP
Deputy Premier

Minister for State Development, Infrastructure and Planning






24 October, 2012

Deputy Premier and Green Scare Tactics





Abbot Point Cumulative Impact Assessment

 

BHP Billiton, North Queensland Bulk Ports Corporation (NQBP), Adani and GVK Hancock Coal (the project partners) are jointly conducting a Cumulative Environmental Impact Assessment (CIA) of proposed developments in the Port of Abbot Point area.

The Port of Abbot Point is one of three existing coal ports in Qld and has been identified by the Qld Government as a preferred port to support further development of the coal export industry.

It is seen as critical to economic development in Central and North Qld, as underlined by the Government’s designation of a State Development Area at Abbot Point.

The Cumulative Environmental Impact Assessment process will be wide ranging and involve 15 detailed studies in the following areas:
·       Shipping;
·       Marine Water Quality;
·       Dredge Plume Modelling
·       Operational Noise;
·       Groundwater;
·       Dust;
·       Underwater Noise;
·       Visual Amenity;
·       Lighting;
·       Coastal Hydrodynamics;
·       Species & Habitat Assessment;
·       Wetland Hydrology & Water Quality
·       Climate Change;
·       Fishing;
·       Joint Offsets Strategy

The report identifies mechanisms to reduce and offset greenhouse gas emissions from the port and ensure port design has accounted for possible climate change effects such as sea level rise. 

The report does not consider greenhouse gas and particulate emissions of transport of coal over vast distances using bunker C fuel oil or combustion of thermal coal.

The Deputy Premier: Jeff Seeney reports that the proposed port expansion was unlikely to affect the integrity of the Great Barrier Reef World Heritage Area. 

Mr Seeney says the reports illustrates that Queensland can have bulk export ports and they can operate with no threat to the Great Barrier Reef. He said the assessment showed that well-managed development could co-exist with a healthy environment.

The Deputy Premier says: “This assessment should put an end to the scare campaigns run by extremist groups whose real agenda is to shut the coal ports and the coal industry as a whole.” 

“Too often they [environmental groups] cry wolf, claiming that any proposed new development will wipe-out entire marine or terrestrial species and threaten the existence of the reef itself.” 

In the case of Abbot Point Mr Seeney says that the report says that:
·       impacts on the marine environment are manageable,
·       that significant impacts on the terrestrial environment are unlikely and;
·       that mitigation and management measures would substantially reduce any potential impacts. 

Mr Seeney said the assessment had been peer reviewed by leading scientists and experts, leaving no room for extremists to distort its findings.  He says that the report highlights that we can have both economic development while protecting the environment because we will insist on world’s best practices and world’s best standards.


~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
A friend has responded......


Regarding the CIA for Abbot Point in your latest newsletter. As usual with mining funded reports they are interesting for what they do not include compared to what is included. They always say impacts can be managed. There is much the CIA appears to have missed that I have repeatedly asked for in public submissions over the years on project proposals in Abbot Point, such as a study on the impacts of a combined flood and storm surge event. Such events are  not unlikely in this location, a narrow low lying coastal plain, because the 6,000 ha wetlands there receive all the runoff during the Wet Season from a 600 square kilometers area of hills to the south of the catchment. Flooding can be severe and usually happens It has overwhelmed wastewater ponds in the past few years (on the spot witness told us that but the port authorities denied it and patched it up before DERM got there).

A big event would sweep wastewaters out to the Reef waters offshore and into the Caley Valley Abbot Point wetland aggregation which, because it is partly tidal, would also carry contaminants out to Great Barrier Reef Marine waters. Future plans call for much filling of these internationally significant wetlands so eventual flooding can only be higher and more damaging.
The CIA report is open for submissions until Dec 4th. We ask that independent engineers and scientists take a look at them at


Can you let your readers know about the chance for submissions at the above website?  Thanks.

15 April, 2012

Public consultation opens for Arrow Energy EIS






Deputy Premier, Minister for State Development, Infrastructure and Planning
The Honourable Jeff Seeney

Thursday, April 12, 2012

Public consultation opens for Arrow Energy EIS

The public is invited to have its say on the environmental impact statement (EIS) for the proposed multi-billion dollar Arrow liquefied natural gas (LNG) plant in Gladstone.

Arrow CSG (Australia) Pty Ltd is proposing to build a 300-hectare LNG facility on Curtis Island, in the Port of Gladstone.

Deputy Premier and Minister for State Development, Infrastructure and Planning Jeff Seeney said the release of the EIS was a major milestone for the project, and if approved, would provide a jobs bonanza for Gladstone.

“The Arrow Energy plant would provide huge economic benefits to the state, and employ up to 3715 people during construction and 450 people during operation,” Mr Seeney said.

“And it would stimulate further investment in the expanding coal seam gas industry, which is steadily increasing its share of the Australian energy market.

“The project’s assessment will be managed by the Coordinator-General who will look at all issues and associated impacts on behalf of the state government.

“If approved, operation of the plant could begin as early as 2017.”

Coordinator-General Barry Broe said it was a large, complex project involving local, state and federal government approval processes and one which would potentially impact on a number of environmental values.

“Consequently, in June 2009 the Coordinator-General declared it a ‘significant project’ for which an EIS is required,” Mr Broe said.

The Curtis Island facility is expected to have a capacity of up to 18 million tonnes of LNG per annum, through a staged development.

A nine kilometre-long feed gas pipeline would be needed from the Gladstone City Gate, traversing Port Curtis via a tunnel under the seabed.

Dredging of the sea bed of Port Curtis and the riverbed at the mouth of the Calliope River is also required to provide access to marine facilities on Curtis Island, and the mainland.

Coordinator-General Barry Broe said he encouraged members of the community to have their say on the EIS.

“The EIS will be available for public comment for six weeks from Monday 16 April 2012.

“For a copy of the EIS, people can download the document from www.arrowenergy.com .

“Alternatively, people can obtain a free copy on DVD or purchase a printed copy by calling 1800 038856 or emailing: arrowlng@arrowenergy.com.au .”

The EIS will also be on public display (subject to local opening hours) between 16 April and 28 May 2012, at:

• Agnes Water Library: 3 Captain Cook Drive, Agnes Water
• Boyne Island Library: Cnr Wyndham and Hampton Drives, Boyne Island
• Calliope Library : Don Cameron Drive, Calliope
• Gladstone Regional Council, 101 Goondoon Street, Gladstone
• Gladstone Regional Library: 39 Goondoon Street, Gladstone
• Miriam Vale Library: 34 Roe Street, Miriam Vale
• National Library: Parkes Place, Canberra
• State Library of Queensland, Cultural Centre, Stanley Place, South Bank, Brisbane

All public submissions must be in writing and received by the Coordinator-General via by 5pm on Monday 28 May, 2012.

Post: The Coordinator-General
c/o EIS Project Manager – Arrow LNG plant
Significant Projects Coordination
Department of State Development, Infrastructure and Planning
PO Box 15009
City East Qld 4002

-ENDS-

Media contact: John Wiseman – 0409 791 281